Q065- Mary MacKillop Penola GLA - Sitio del proyecto público
-
16th julio 2025, Traffic flow and Site parking
Hi All, Please ensure all road rules and site signage are followed. Speed limit is to be UNDER 10 KMH.
Please make sure that you are not parking on the site compound. All parking is to be in the nominated contractor area. -
26th febrero 2025, Daily Hazard Report
Daily Hazard Report
Excavations
- Open Trenches
- Mobile Plant Movements
- Slips, Trips and Falls
Footing steel install
- Slips, Trips, Falls
- Manual Handling
- Working around loose edges.
- Metal cutting eye protection
- Sharp metal cut edges.
Ensure correct lifting techniques
Take 5 before starting activities
Ensure relevant SWMS are signed prior to commencing works
Tiempo actual del emplazamiento
Última actualización en: 2:21
Temperatura: 22C (Aplicación 24C)
Velocidad del viento: 11Km / h
Max. Viento: 20Km / h @0:21
Lluvia desde las 9 a. m.: 0,0mm
Temperatura mínima: 22C @2:20
Temperaturas máximas: 34C @15:59 01/02/2026
Ráfaga: 13Km / h
Ráfagas máximas: 24Km / h @0:21
Ubicación de la observación - Toowoomba, QUEENSLAND
Huso horario - hora estándar de Australia oriental
Pronóstico - lunes, 2 febrero
Partly cloudy.
Min: 16C Max: 25C
Probabilidad de lluvia: 10%
Pronóstico Ubicación - Toowoomba, QUEENSLAND
Huso horario - hora estándar de Australia oriental
Mañana - martes, 3 febrero
Partly cloudy.
Min: 15C Max: 26C
Probabilidad de lluvia: 10%
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.